20) FIRST WORK DAY! - Water damage repairs begin - December 4, 2000
Contractor Ed Kostak and his son start work on exterior areas of the Squires Tavern that are being damaged by water. The first priority is a section of the east wall which has extensive rot to the clapboards, sheathing, studs and some rot in the sill. Clapboards, sheathing and studs are removed. Walt Landgraf and also a Project Green work crew of about ten (from a minimum security prison in Connecticut) assist in disposing the damaged wood. Click on photos below to see the this work in progress.