November 2001 - Posts

  • 127) Grant activity

    127)  Grant activity - November 30, 2001
                     Leslie Cosgrove has completed the STEAP (Small Town Economic Assistance Program) grant letter and has it signed by Historical Society officers and local town and state officials.  This letter initiates the application for a large grant to support the work at the Squires Tavern.

    Posted Nov 30 2001, 01:49 PM by Paul with no comments
    Filed under: ,
  • 126) Squires Tavern work party

    126)  Squires Tavern work party - November 28, 2001
                     Volunteers work on the bulkhead entrances to the cellar and also tear out and remove most of the modern kitchen cabinets.  Some electrical wiring is removed and work is started on the future bathroom.  Scrape wood is saved for the wood stove that will be temporarily installed in the front kitchen area. 

  • 125) Squires Tavern contractor work

    125)  Squires Tavern contractor work - November 28, 2001
                     ROOF SHINGLING IS COMPLETED!  Contractor Mike Cote has nailed the last shingle on the roof of the Squires Tavern today.  We now have a new roof of red cedar shingles which we hope will last for many decades.  A big project and a major area of concern is put to rest.


    Photo- the last shingles are put on the roof of the Tavern.

     

  • 124) Squires Tavern committee meeting

    124)  Squires Tavern committee meeting - November 24, 2001
                     Major areas of discussion: 1) how to rebuild/repair the two bulkhead entrances to the cellar in an historically accurate manner; 2) decisions are made on how to proceed on construction details including the addition of a second flue and thimble in the ell chimney and on several door and window issues; 3) Walt has done further research on Bela Squires regarding the presence of a second blacksmith shop near the tavern. 

  • 123) Squires Tavern contractor work

    123)  Squires Tavern contractor work - November 24, 2001
                     Progress made by contractors for the week ending November 24: Mike Cote has finished shingling the back roof of the main part of the tavern and has started flashing on the front portion.  Ed Kostak has completed about 90% of the clapboard work on the back of the front kitchen.  Bill Parsons is progressing with chimney repair work.

  • 122) Squires Tavern support work

    122)  Squires Tavern support work - ongoing
       
                 Walt Landgraf and Dave Ravasio spend a significant amount of time on critical aspects of the project on almost a daily basis.  This work includes materials research, working with contractors,  meeting with potential contractors and historic experts, meeting with town officials such as the building inspector, analyzing historic aspects of the building as they are revealed during the work, planning and suggesting priorities for work to be done and numerous other tasks.  This work is ongoing and has been especially heavy during the last few months.

  • 121) Squires Tavern work party

    121)  Squires Tavern work party - November 17, 2001
                     Volunteers cut and remove brush from the back yard of the Squires Tavern property.

More Posts Next page »
Terms Of Service | Privacy Policy
All Copy and Images Copyright © 2017 Barkhamsted Historical Society All Rights Reserved.
Powered by Community Server (Non-Commercial Edition), by Telligent Systems