  • 204) Squires Tavern contractor work

    204) Squires Tavern contractor work - week ending June 29, 2002 Plumbing contractor Clayton Webb has moved the sink to the new kitchen location. He has also removed a radiator and installed a hot water control valve and a hose connection in the basement. Electrical contractor Bob Morse has finished the...
    Posted to Work Log (Weblog) by Paul on 06-29-2002
  • 198) Squires Tavern contractor work

    198) Squires Tavern contractor work - week ending June 15, 2002 Masonry work by Bill Parsons is completed, including the last brick on the main chimney. Dave's Painting has finished priming the exterior of the building and finished a good portion of the second coat.
    Posted to Work Log (Weblog) by Paul on 06-15-2002
  • 194) Squires Tavern contractor work

    194) Squires Tavern contractor work - week ending June 8, 2002 Ed Kostak installs metal studs around the fireplaces in the ell. These are required by fire code and will support the blueboard and plaster which will be added later in the summer. Masonry work by Bill Parsons is nearing completion on the...
    Posted to Work Log (Weblog) by Paul on 06-08-2002
  • 187) Squires Tavern contractor work

    187) Squires Tavern contractor work - week ending May 25, 2002 Painting starts! Painters from Dave's Painting begin scraping and priming the exterior of the Squires Tavern on Tuesday, May 21. In about two weeks the Tavern will look pretty spiffy. Dave also finishes another group of windows (scraping...
    Posted to Work Log (Weblog) by Paul on 05-25-2002
  • 177) Preliminary inspection by plaster contractor

    177) Preliminary inspection by plaster contractor - April 18, 2002 Plaster contractor Mike Zordan visits. Walt Landgraf and Mike cover all the rooms that will have extensive plaster replacement done. The wall areas have had much of the preparation work already completed (sheetrock removed, etc) over...
    Posted to Work Log (Weblog) by Paul on 04-18-2002
  • 174) Squires Tavern contractor work

    174) Squires Tavern contractor work - week ending April 13, 2002 Carpenter Ed Kostak and son have finished both the north and south hatchways (except for some small details). They have completed the interior window and door trim in the rooms that will have plaster work later in the year. Also completed...
    Posted to Work Log (Weblog) by Paul on 04-13-2002
  • 172) Squires Tavern contractor work

    172) Squires Tavern contractor work - week ending April 6, 2002 Carpenter Ed Kostak and son continue to add trim to several rooms downstairs including chair rail, window trim and door trim. This trim is identical to the original trim, pieces of which can still be found in some locations of the building...
    Posted to Work Log (Weblog) by Paul on 04-06-2002
Page 5 of 7 (66 items) « First ... < Previous 3 4 5 6 7 Next >
Terms Of Service | Privacy Policy
All Copy and Images Copyright © 2020 Barkhamsted Historical Society All Rights Reserved.
Powered by Community Server (Non-Commercial Edition), by Telligent Systems